Initiate Switchover
Once triggered, whether manually or automatically, the switchover process itself is fully automated.
Note: Though the following steps show Exchange scenario screens as examples, the procedure is similar for all server types.
To initiate manual switchover
- Open the Manager and select the desired scenario from the Scenario pane. Verify it is running.
- Click on the Perform Switchover button, or select from the Tools menu the Perform Switchover option:
- Click OK on the Perform Switchover confirmation message. This procedure initiates a switchover from the Master server to the Replica server:
- After the switchover is completed the scenario stops:
- Now, the Master becomes passive and the Replica becomes active
A confirmation message appears.
Detailed information about the switchover processes is located in the Events pane during switchover.
Note: The only case in which the scenario may continue to run after switchover is when automatic reverse replication is defined as Start automatically.
In the Event pane a message appears, informing you that Switchover completed, and then that the Scenario has stopped.